Processing Authority: Special Equipment Supervising Department of Shanghai
Quality and Technical Supervision Bureau
Application Formality: 1. Basic requirements: (1) The boiler should be
produced by licensed manufacturer; (2) The design of the stokehold shall be
approved; (3) The boiler should be installed by licensed enterprise; (4)
The boiler should be appraised to be eligible; (5) Enough stokers are
equipped. 2. Documents for application: (1) Opinion paper on
stokehold; (2) Constructing registration form of the boiler installing
enterprise; (3) Boiler technology registration book (filled); (4) Initial
examining report of the boiler; (5) Operating status examining report of the
boiler; (6) Water quality examining report of the boiler; (7) Fuel (Gas)
Boiler debug report; (8) Water processing equipment debug report; (9)
Certificate of the stokers and water quality testing staff (copies); (10)
Relevant safety managing system of the enterprises that using boilers.
Processing Procedures: 1. After installing and appraising the boilers,
the enterprise should make the registration procedures with relevant
documents; 2. The processing authority audit the documents; 3. Take
registration procedures and issue Boiler Using Registration Certificate.
Charging Standard & Basis: Standard: RMB 5 for per
certificate Basis: Notice on Verifying Administration Charging Items and
Standards of Shanghai Labor System by Shanghai Pricing Bureau and Shanghai
Finance Bureau (Hu Jia She [1992] No. 177)
Processing Address: Room 1005, 10th floor, No. 1227 Chang-Le Road
Processing Basis: 1. Interim Regulations on Safety Supervising of Boiler
and Pressure Container 2. Rules on Safety Technology Supervising of Steam
Boiler 3. Rules on Safety Technology Supervising of Hot Water Boiler 4.
Rules on Safety Technology Supervising of Thermal Oil Heater 5. Rules on
Safety Technology Supervising of Small Boiler and Normal Pressure Hot Water
Boiler 6. Registration Regulations of Using Boiler
Contact Tel: 54049194¡¢54045500¡Á2003
Processing Time: Tuesday and Thursday 8:30-16:30
Time Limit for Processing: 1 working day for those who meet the
requirements
Qualified Application Subject pressed boiler and normal pressure hot water
boiler installed and bestowed in Shanghai.
|