Execution authority: Shanghai Civil Defense Office Application procedure:
1. "Shanghai Approval Form of Dismantlement of Civil Defense Facility", in three
copies; 2. Copy of approval document of on-ground construction; 3. Copy
of overall plan drawing (or land map) with the location of dismantlement
highlighted; 4. Copy of dismantlement agreement signed between the
dismantling organization and the owner of the civil defense
facility. (Copies submitted shall be affixed with official seal or the
special seal for documents management page by page) Execution
procedure: ¡¡¡¡1. The dismantling organization shall submit the
application; ¡¡¡¡2. The general service window shall accept the
application; ¡¡¡¡3. The municipal Civil Defense Office shall take internal
examinatin and issue the "Shanghai Approval Form of Dismantlement of Civil
Defense Facility"; ¡¡¡¡4. If the result of examination is to undertake
compensative building, the applicant shall obtain the "Shanghai Approval Form of
Dismantlement of Civil Defense Facility"; ¡¡¡¡5. If the result of examination
is to compensate for the dismantlement with money, the applicant shall pay the
compensation fee as required in check to the general service window and then
obtain the "Shanghai Approval Form of Dismantlement of Civil Defense Facility"
and the receipt of compensation fee for
dismantlement. ¡¡¡¡<STRONG>Standard of compensative building or money
compensation²¹½¨»ò²¹³¥±ê×¼</STRONG> ¡¡¡¡For the dismantlement of public civil
defense facilities or other civil defense facilities built upon the investment
of national government, the dismantling organization shall take compensative
building or money compensation as following standard: ¡¡¡¡1. Dismantlement of
graded civil defense facility: take compensative building according to the
construction area and grade of original civil defense facility, or, if confirmed
inapplicable for compensative building, pay money compensation to the municipal
Civil Defense Office at the standard of 3500 yuan/square meter for
dismantlement; ¡¡¡¡2. Dismantlement of non-graded civil defense facility that
is made of reinforced concrete: take compensative building according to the
grade at least of the lowest grade and the construction area at least of two
third of the original area, or, if confirmed inapplicable for compensative
building, pay money compensation to the municipal Civil Defense Office at the
standard of 2300 yuan/square meter for dismantlement;
¡¡¡¡3. Dismantlement of non-graded civil defense facility that is made of brick
and reinforced concrete: take compensative building according to the grade at
least of the lowest grade and the construction area at least of one third of the
original area, or, if confirmed inapplicable for compensative building, pay
money compensation to the municipal Civil Defense Office at the standard of 1150
yuan/square meter for dismantlement;
¡¡¡¡For the dismantlement of the civil defense facility excluded from foregoing
stipulations, the dismantling organization shall negotiate the compensation with
the owner of the civil defense facility. Standard and basis of charge:
Submitted to: Execution address: First Floor, 593 Fuxingzhong
Road£¬Post code: 200020 audituser £º Basis of execution: 1. Article 28 of
"Law of the People's Republic of China on Air Defense"; 2. Article 42 of
"Ordinance of Shanghai on Civil Defense"; 3. Article 17 and 18 of "Measures
of Shanghai on Construction and Use of Civil Defense Facilities"; 4. "Reply
on Adjustment of Charge for Use and Compensation for Dismantlement of Civil
Defense Facility in Shanghai", issued by Shanghai Price Bureau and Shanghai
Finance Bureau. Contact phone: 54662088 Website: Duration of
service: Full working day from Monday to Thursday, morning of
Friday 8:30-11:30 and 13:30-16:30
Time limit: The application shall be settled within 10 working days since
being accepted. Applicant's qualification: the dismantling organization able
to dismantle graded civil defense facilities or the non-graded civil defense
facility with at least 500 square meters. (The application for dismantling the
non-graded civil defense facility shall be submitted to the local
district/county Civil Defense Office in charge of the facility).
|