Execution authority: Acceptance Division of Fire Supervision Department of
Shanghai Fire Bureau, and Fire Supervision Divisions (Sections) of
district/county Public Security (Branch) Bureaus Application procedure: 1.
"Shanghai Application Form for Acceptance of Fire Protection Facilities upon
Completion of Construction" in paper form with official seal affixed and in
electronic form in floppy disk. The paper form shall be signed by the legal
representative or the principal and affixed with the legal person's seal of the
organization. All construction organizations for specific tasks shall clearly
specify the range of projects that they undertake respectively; 2. Lists and
quality certification of construction parts, fireproof performance of materials
and fire protection products; 3. Copies of all pieces of "Conclusion of
Examination of Fire Protection Design for Construction Project" issued by the
original authorities for public security and fire protection; 4. Report on
availability of fire protection facilities upon qualified commissioning in paper
form and in electronic form in floppy disk. This report is with fixed format and
shall be signed by the commissioning staff and affixed with the official seal of
the organization that the commissioning staff serves for. (The simple indoor
decoration shall be evidenced by the certification issued by the property
management organization stating "the fire protection facilities keep unchanged
or has been availed"); 5. Logic relation chart or descriptive text of the fire
alarm interlink control system, with the official seal of the organization that
conducts the commissioning affixed; 6. Original copy of name list of on-duty
staff in fire control room, with the official seal of legal person of the
property management organization affixed; 7. Record of painting of fire
resistant materials on steel structures. Execution procedure: The authorities
for public security and fire protection shall dispatch suitable employees to
examine the construction within 10 working days and issue the "Comments on
Acceptance of Fire Protection Facilities of Construction Project" to the
qualified within 7 working days since finishing the examination. Standard
and basis of charge: free Submitted to: Shanghai Public Security Bureau and
Fire Bureau Execution address: Construction Examination Division, Key
Project Division, Danger Management Division and Water Supervision Station of
Fire Supervision Department of Shanghai Fire Bureau
Basis of execution: "Law of the People's Republic of China on Fire
Protection", "Regulations of Shanghai on Fire Protection" and "Regulations on
Supervision and Management of Fire Protection of Construction Projects"
Contact phone: Please refer to "Execution address" Website:
Duration of service: Please refer to "Execution address" Time limit: The
authorities for public security and fire protection shall make field
investigation within 10 working days since receiving the application and issue
the written comments within 7 working days after finishing the examination.
Applicant's qualification: For the project of building, expansion,
rebuilding and indoor upholstery in Shanghai, the corresponding fire protection
facilities shall be examined and accepted.
|