Examination of the Construction Drawing Design of Fire System of Construction Project at Equipment Period
(06/15/2005)

Execution authority: Construction Examination Division, Key Project Division, Danger Management Division and Water Supervision Station of Fire Supervision Department of Shanghai Fire Bureau £¬Fire Supervision Divisions (Sections) of district/county Public Security (Branch) Bureaus

Arrangement of project examinations

(I) Projects to be examined by Construction Examination Division of Fire Supervision Department of Shanghai Fire Bureau

1. Design of fire system of the construction project planned by municipal planning bureau and the key municipal construction projects;
2. High public buildings of first type (or the high public buildings over 100 meters in Pudong New District);
3. The resident building over 100 meters high or with the average construction area of every household more than 150 square meters;
4. The Type-one commercial-resident building with the store at bottom at least two floors high;
5. Type C, D and E industry projects with the total investment more than 300 million yuan;
6. Type A and B warehouse with the construction area of single buidling more than 1 thousand square meters; Type A and B workshop building with the construction area of single building more than 2 thousand square meters;
7. Gas or liquid storage vessel independently built and with the fire risk over Type C (excluding Type C);
8. New municipal construction projects of subway, tunnel, railway station, wharf and airport;
 (II) The projects to be treated as one of municipal key fire protection focuses other than above shall be examined by Key Project Division and Danger Management Division of Fire Supervision Department of Shanghai Fire Bureau; the gas station or petrol station for automobiles shall be examined by Danger Management Division of municipal Fire Bureau; the ships, wharfs and water-related operations shall be examined by Water Supervision Station of Fire Supervision Department of Shanghai Fire Bureau.
(III) Other projects shall be examined by the Fire Supervision Divisions (Sections) of district/county Public Security (Branch) Bureaus and the authority for public security authorized by Shanghai Fire Bureau.

Application procedure: 1. "Shanghai Application Form for Examination of the Design of Automatic Extinguishing Facilities of Construction Projects", with the copy of "Comments on Design Examination of Fire System of Construction Project" issued by the authorities for public security and fire protection upon examination of some parts of the construction project;
2. General map, plan view and system chart and explanation of fire supply system (indoor fire hydrant and automatic sprinkling system);
3. Plan view, system chart and explanation of automatic fire alarm system;
4. Plan view, system chart and explanation of anti-fume system;
5. Plan view, system chart and explanation of other fixed extinguishing systems;
6. The applicant shall submit the CDs containing the materials at the reception window of Fire Bureau, but CDs are not compulsory for following projects:
 (1) Common public buildings with at most 3 stories high and the most construction area of every story not more than 200 square meters, except public entertainment places;
 (2) Common resident buildings at most 6 stories high, except villa and garage;
 (3) Type C workshop building or warehouse with the construction area of single building not more than 400 square meters; Type D and E workshop building or warehouse with the construction area of single building not more than 1 thousand square meters;
 (4) Auxiliary facilities (including the transformation and distribution rooms, boiler rooms, gas pressure regulating station or cabinet, bus station, duty room of guards, external wall and awnings);
    The construction drawing design on automatic fire system shall be signed by the designer with the "Qualification Certificate of National Professional Fire Protection Examination to Specific Engineering Designers for Fire Protection Design".
Execution procedure: After examining the application documents, the authorities for public security and fire protection shall issue the "Comments on Design Examination of Fire System of Construction Project (Equipment Period)".
Standard and basis of charge: free
Submitted to: Shanghai Public Security Bureau and Fire Bureau
Execution address: Construction Examination Division, Key Project Division, Danger Management Division and Water Supervision Station of Fire Supervision Department of Shanghai Fire Bureau

Basis of execution: "Law of the People's Republic of China on Fire Protection", "Regulations of Shanghai on Fire Protection" and "Regulations on Supervision and Management of Fire Protection of Construction Projects".
Contact phone: Please refer to "Execution address"
Website: 
Duration of service: Please refer to "Execution address"
Time limit: Since acceptance of application, the authorities for public security and fire protection shall issue the "Comments on Design Examination of Fire System of Construction Project (Equipment Period)" within 20-30 working days.
Applicant's qualification: For the project of building, expansion and rebuilding in