Execution authority: Construction Examination Division, Key Project Division,
Danger Management Division and Water Supervision Station of Fire Supervision
Department of Shanghai Fire Bureau £¬Fire Supervision Divisions (Sections) of
district/county Public Security (Branch) Bureaus
Arrangement of project examinations
(I) Projects to be examined by Construction Examination Division of Fire
Supervision Department of Shanghai Fire Bureau
1. Design of fire system of the construction project planned by municipal
planning bureau and the key municipal construction projects; 2. High public
buildings of first type (or the high public buildings over 100 meters in Pudong
New District); 3. The resident building over 100 meters high or with the
average construction area of every household more than 150 square meters; 4.
The Type-one commercial-resident building with the store at bottom at least two
floors high; 5. Type C, D and E industry projects with the total investment
more than 300 million yuan; 6. Type A and B warehouse with the construction
area of single buidling more than 1 thousand square meters; Type A and B
workshop building with the construction area of single building more than 2
thousand square meters; 7. Gas or liquid storage vessel independently built
and with the fire risk over Type C (excluding Type C); 8. New municipal
construction projects of subway, tunnel, railway station, wharf and
airport; (II) The projects to be treated as one of municipal key fire
protection focuses other than above shall be examined by Key Project Division
and Danger Management Division of Fire Supervision Department of Shanghai Fire
Bureau; the gas station or petrol station for automobiles shall be examined by
Danger Management Division of municipal Fire Bureau; the ships, wharfs and
water-related operations shall be examined by Water Supervision Station of Fire
Supervision Department of Shanghai Fire Bureau. (III) Other projects shall be
examined by the Fire Supervision Divisions (Sections) of district/county Public
Security (Branch) Bureaus and the authority for public security authorized by
Shanghai Fire Bureau.
Application procedure: 1. "Shanghai Application Form for Examination of the
Design of Automatic Extinguishing Facilities of Construction Projects", with the
copy of "Comments on Design Examination of Fire System of Construction Project"
issued by the authorities for public security and fire protection upon
examination of some parts of the construction project; 2. General map, plan
view and system chart and explanation of fire supply system (indoor fire hydrant
and automatic sprinkling system); 3. Plan view, system chart and explanation
of automatic fire alarm system; 4. Plan view, system chart and explanation of
anti-fume system; 5. Plan view, system chart and explanation of other fixed
extinguishing systems; 6. The applicant shall submit the CDs containing the
materials at the reception window of Fire Bureau, but CDs are not compulsory for
following projects: (1) Common public buildings with at most 3 stories
high and the most construction area of every story not more than 200 square
meters, except public entertainment places; (2) Common resident
buildings at most 6 stories high, except villa and garage; (3) Type C
workshop building or warehouse with the construction area of single building not
more than 400 square meters; Type D and E workshop building or warehouse with
the construction area of single building not more than 1 thousand square
meters; (4) Auxiliary facilities (including the transformation and
distribution rooms, boiler rooms, gas pressure regulating station or cabinet,
bus station, duty room of guards, external wall and awnings);
The construction drawing design on automatic fire system
shall be signed by the designer with the "Qualification Certificate of National
Professional Fire Protection Examination to Specific Engineering Designers for
Fire Protection Design". Execution procedure: After examining the application
documents, the authorities for public security and fire protection shall issue
the "Comments on Design Examination of Fire System of Construction Project
(Equipment Period)". Standard and basis of charge: free Submitted to:
Shanghai Public Security Bureau and Fire Bureau Execution address:
Construction Examination Division, Key Project Division, Danger Management
Division and Water Supervision Station of Fire Supervision Department of
Shanghai Fire Bureau
Basis of execution: "Law of the People's Republic of China on Fire
Protection", "Regulations of Shanghai on Fire Protection" and "Regulations on
Supervision and Management of Fire Protection of Construction
Projects". Contact phone: Please refer to "Execution
address" Website: Duration of service: Please refer to "Execution
address" Time limit: Since acceptance of application, the authorities for
public security and fire protection shall issue the "Comments on Design
Examination of Fire System of Construction Project (Equipment Period)" within
20-30 working days. Applicant's qualification: For the project of building,
expansion and rebuilding in |