Home >> Service for Business >> Waters >> Service Guide
The Approval of Water Quota Check (underground water)
(06/15/2005)

Processing Authority: Shanghai Municipal Administration of Water Supply or district (county) level water administration bureau
Application Procedures:
1. Letter of application for quota of water use.
2. Approval of project, permit of construction project planning and other relevant documents.
3. Name, type, quantity and water use quantity of equipments that use water.

Handling Procedures: <FONT face=ËÎÌå size=3><IMG alt=302.jpg  SRC="<!--InsertImg--$$OBJ$$,·¢²¼Í¼Ïñ,3178-->"></FONT>
Charging Standards & Basis:
Submitted to: Shanghai Municipal Water Affairs Administration Bureau
Address: Floor 5, #261 Da Lian Road West
audituser £º
According to: Article 11 of "Measures on the Administration of Urban Water Conservation", Article 35 of "Regulations of Shanghai Municipality on the Administration of Water Supply", Article 7 of "Measures of Shanghai Municipality on the Administration of Water Conservation"
Telephone: 65079958
Website: 
Working Hours: Monday to Friday 8:30~17:00
Duration of Procedures: Fifteen working days
Qualification of Applicants: Water use enterprises