Processing Authority: Municipal, district (county) level water administration
departments Application Procedures: 1. Approval of construction
project 2. Feasibility study report of the project and initial design. 3.
Report on project acceptance check.
Handling Procedures:
Charging Standards & Basis: Submitted
to: Shanghai Municipal Water Affairs Administration Bureau Address: No.1,
Lane 955, Ju Jia Qiao Road audituser£º According to: Article 20 of
"Regulations of Shanghai Municipality on the Administration of
Rivers" Telephone: 58995873 Website: Working Hours: Monday to Friday
8:30~16:30 Duration of Procedures: Ten working days after the project is
accepted Qualification of Applicants: Construction enterprises
|