Home >> Service for Business >> Waters >> Service Guide
The Filing of Construction Projects With Controlled Areas Along Rivers
(06/15/2005)

Processing Authority: Municipal, district (county) level water administration departments
Application Procedures:
1. Approval of construction project
2. Feasibility study report of the project and initial design.
3. Report on project acceptance check.

Handling Procedures:

Charging Standards & Basis:
Submitted to: Shanghai Municipal Water Affairs Administration Bureau
Address: No.1, Lane 955, Ju Jia Qiao Road
audituser£º
According to: Article 20 of "Regulations of Shanghai Municipality on the Administration of Rivers"
Telephone: 58995873
Website:
Working Hours: Monday to Friday 8:30~16:30
Duration of Procedures: Ten working days after the project is accepted
Qualification of Applicants: Construction enterprises