The Approval of Construction to Connect Self-constructed Water Drainage Facilities With Public Water Drainage System
(06/15/2005)
Processing Authority: Municipal, district (county) level water drainage administration bureaus (or other designated administrative bureaus)
Application Procedures: 
1. Construction plan of the water drainage facilities.
2. Design of the water drainage system.
3. Planning reference of the construction to connect into public drainage system.
Handling Procedures: <FONT face=ËÎÌå size=3><IMG alt=333.jpg  SRC="<!--InsertImg--$$OBJ$$,·¢²¼Í¼Ïñ,3161-->"></FONT>
Charging Standards & Basis:
Submitted to: Shanghai Municipal Water Affairs Administration Bureau
Address: #180 Xia Men Road
audituser £º
According to: Section 2 and 3 Article 11 of "Regulations of Shanghai Municipality on the Administration of Water Drainage"
Telephone: 63226148
Website: 
Working Hours: Monday to Friday 8:30~16:30
Duration of Procedures: Twenty working days
Qualification of Applicants: Construction companies