The Approval of Construction and Pilling Within The Controlled Area of Huang Pu River Flood Prevention Walls
(06/15/2005)
Processing Authority: Shanghai Municipal Flood Prevention Wall Construction and Administration Office
Application Procedures:
1. Written application for the construction within the controlled area (indicating reason, time and scope of construction).
2. Approval of the construction plan and floor layout (1:500).
3. Flood prevention responsibility agreement during the construction between construction enterprises and enterprises responsible for flood control.
4. Measures on the protection of the wall put forward by the original designing company.
Handling Procedure: <FONT face=ËÎÌå size=3><IMG alt=344.jpg  SRC="<!--InsertImg--$$OBJ$$,·¢²¼Í¼Ïñ,3032-->"></FONT>
Charging Standards & Basis:
Submitted to: Shanghai Municipal Water Affairs Administration Bureau
Address: # 80 Wu Song Road
audituser £º
According to: Article 12 of "Measures of Shanghai Municipality on the Protection of Flood Prevention Wall Along Huang Pu River"
Telephone: 63257567
Website: 
Working Hours: Monday to Friday 9:00~16:30
Duration of Procedures: Fifteen working days
Qualification of Applicants: Any applicant