Home >> Service for Business >> Waters >> Service Guide
The Checking and Approval of Construction on Important Riverway Dike
(06/15/2005)
Processing Authority: Administration bureaus of dike or flood prevention wall
Application Procedures:
The following documents are to be submitted for the approval: 1. Written application. 2. Project design for the construction. 3. Relevant flood prevention measures to be taken.
The following documents are to be submitted for project acceptance filing:
1. Construction schedule provided by the construction company.
2. Inspection report from relevant departments on the temporary measures of flood prevention.
Handling Procedures: <FONT face=ËÎÌå size=3><IMG alt=329.jpg  SRC="<!--InsertImg--$$OBJ$$,·¢²¼Í¼Ïñ,3040-->"></FONT>
Charging Standards & Basis:
Submitted to: Shanghai Municipal Water Affairs Administration Bureau
Address: Floor 17, #1017 Lao Shan Road West, Pudong New Area
audituser £º
According to: Article 30 of "Regulations of Shanghai Municipality on the Administration of Riverway"
Telephone: 58773226
Website: 
Working Hours: Monday to Friday 9:00~17:00
Duration of Procedures: Fifteen working days
Qualification of Applicants: Construction enterprises