Transaction department: Administrative Department on Rail Transport of
Shanghai Application formalities: (I) materials for application for the
project: 1. Approval documents on establishing the projects from relevant
organs; 2. Certificates on right of use of land at construction base (copies)
or letter of ratification on land for construction use (copies); 3. Name, use
of the project and planned dates for starting and finishing construction
work; 4. Basic structure, floor height and construction form of the buildings
as well as basic information on other operation projects; 5. Geological
location of the project and its relative position with rail transport
lines. (II) Materials for technical examination 1. Master plan of the
construction (to indicate its position relation with rail transport lines on a
1:500 relief map); 2. Texts of preliminary design and expanded
designing; 3. A set of drawing respectively for architectural drawing and
construction drawing; 4. A set of document on pile foundation and fencing
facility design; 5. Report on geologic prospecting; 6. Relevant materials
on impact of the operation on rail transport facilities or on rail transport
construction in the future; 7. Construction design on digging footing groove
and support, including safety precautions taken in operation; designing plan and
construction measures for meeting controlling indicators of horizontal shift and
vertical subsidence of rail transport facilities; Examination and approval on
projects of operation in safety preservation zone on rail transport lines of
Shanghai.
Application instruction I. The transaction is based on the following laws
and regulations: "Regulations on Rail Transport Management of
Shanghai" "Provisional Regulations on Management of Safety Protection Zone on
Rail Transport Lines of Shanghai" II. Scope of application Examination and
approval, supervision as well as relevant management on projects of operation in
safety protection zone on rail transport lines whose construction is finished or
those under construction of Shanghai. III. Range of safety protection
zone (I) Within 50m from the flank of outer side lines of underground
stations and tunnels; (II) Within 30m from the flanks of outer side lines of
stations on the ground, elevated stations and of rail lines; (III) Within 10m
from the flanks of outer side lines of entrances and exits, ventilations booth
and transformer substations, etc. IV. Operation contents To do the
following operation work within range of safety protection zone on rail
transport lines, the operation plans must be approved by administrative
department on rail transport of the city, and corresponding safety precautions
must be taken: (I) To construct or dismantle buildings; (II) To do such
construction operation as piling, excavation, explosion, erection, precipitation
and foundation improvement, etc.; (III) Other activities on increasing or
reducing load of large area. V. Transaction department: Administrative
Department on Rail Transport of Shanghai VI. Materials for application
(¢ñ) Materials for application for the project: 1. Approval documents on
establishing the projects from relevant organs; 2. Certificates on right of
use of land at construction base (copies) or letter of ratification on land use
for construction use (copies); 3. Name, use of the project and planned dates
for starting and finishing construction work; 4. Basic structure, floor
height and construction form of the buildings as well as basic information on
other operation projects; 5. Geological location of the project and its
relative position with rail transport lines. (¢ò) Materials for technical
examination 1. Master plan of the construction (to indicate its
position relation with rail transport lines on a 1:500 relief map); 2. Texts
of preliminary design and expanded designing; 3. A set of drawing
respectively for architectural drawing and construction drawing; 4. A set of
document on pile foundation and fencing facility design; 5. Report on
geologic prospecting; 6. Relevant materials on impact of the operation on
rail transport facilities or on rail transport construction in the future; 7.
Construction design on digging footing groove and support, including safety
precautions taken in operation; designing plan and construction measures for
meeting controlling indicators of horizontal shift and vertical subsidence of
rail transport facilities; Examination and approval on projects of operation in
safety preservation zone on rail transport lines of Shanghai. 8. Other
relevant materials.
Transaction procedures: (¢ñ) Construction units of the projects file in an
application to the municipal administrative department on rail transport, and
submit materials according to regulations. (¢ò) The municipal department on
rail transport is to do verification work on the application materials after
getting the application, and make a decision on accepting or not accepting the
application within 2 working days. (¢ó) Those whose application is accepted
are to be given a notice on technical examination and informed of materials to
be submitted for the examination work; the notice on technical examination and
application materials are also to be sent to relevant units for technical
examination work. (¢ô) Relevant units on technical examination are to produce
opinions from the examination work within 15 working days, and then report to
the municipal administrative department on rail transport. (¢õ) The municipal
administrative department on rail transport is to make a decision on approving
or not approving operation plan based on opinions from technical examination
within 5 working days, and notify construction units and relevant unit for
technical examination in written form. (¢ö) Before starting construction work,
the construction units should go through procedures for monitoring and
supervising operation within safety protection zone on rail transport lines with
construction unit of rail transport projects or with operator of rail transport
lines, and then do construction work according to authorized operation plan.
Charging standard and its basis: Submit to: Address: F14, No.922
Hengshan Road Audituser: The transaction is based on: "Regulations on
Rail Transport Management of Shanghai" "Provisional Regulations on Management
of Safety Protection Zone on Rail Transport Lines of Shanghai" Tel.:
64481188*8031 Tel. for supervision: 64472392
Website: Time for transaction: Mondays, Wednesdays, and Thursdays
9£º00~11£º00, 13:30~16£º00 Time limit for transaction: Applicant
qualifications: Examination and approval, supervision as well as relevant
management on projects of operation fir safety protection zone on rail transport
lines whose construction is finished or those under construction in Shanghai.
|