Responsible Departments: Shanghai Construction and Management Commission
Department ofConstruction Planning and Science and Education Handling
Procedure: I. Approval of the feasibility study report of the project. II.
Opinion on project location selection and requirement on planning (land
agreement on auctioned land). III. Approval of planning design (including
floor plan and major technical parameter). IV. Opinions from relevant
departments and urban infrastructure departments. Evaluation on environment
impact. V. Complete preliminary design provided by qualified designing
companies (Shall meet the requirement of Shanghai Construction Plan, including
word description, blueprint, budgetary estimate, The height shall meet certain
requirement.) Design in the charge of several companies need a consolitated
document. Opinions from local consulting firms is needed for the design carried
out by foreign companies. VI. Relevant land usage approval. VII.
Application of the construction company for preliminary approval.
Handling Procedure:
align=justify>กกกก I. For ordinary projects, the handling departments
will check the documents and decide according to the documents whether the
application meet the requirement of preliminary approval. If it does, a
questionnaire will be disributed or a coordinating meeting will be held to
collect the opinion from relevant administrative departments and urban
infrastruture departments. It will be dcided after comprehensive coordination
whether the preliminary design of the project meets certain standards and
requirements. For projects with more than 50,000 squre meters or more than
20,000 square meters for individual buildings or hgiher than 100 meters,
technical consultation from experts I needed in principle. (Shanghai
Construction Committee and Science and Technology Commission will be entrusted
to evaluate the design, structure and equipment of the project.) Shanghai
Municipal Construction and Management Commission and Science and Technology
Commission will need to evaluate the construction, structure, equipment and
budgetary of the project if the project is financed through municipal
budget. II. Commercial projects whose land is acquired through auction, the
construction company shall submit relevant documents. The handling departments
shall collect the opinion from relevant departments and urban infrastructure
departments and reply after overal coordination.
According to: Circular of the State Planning Commission on Reiterating The
Procedure of Basic Construction Projects (J.T.Z. (2999) No. 693), Circular of
the Stae Planning Commission on Budgetary Estimate of Large to Medium Sized
Basic Construction Projects ( J.J.S. (1996) No. 1154), "Regulations of Shanghai
Municiplity on Construction Market Admiistration", "Several Opinions on
Improving the Quality of Large to Medium Sized Basic Construction Project
Preliminary Design", "Circular of Shanghai Municipality on the Approval
Preliminary Design of Construction Projects"
During of Procedure: I. For general projects, approval on the preliminary
design will be issued within twenty working days after the receipt of all
documents. (If the building is too high, approval from aseismatic experts is
needed. Then the approval time will be prolonged.) II. For commercial
projects whose land is acquired through auction, decisions will be made within
twenty working days after the receipt of all documents. It takes ten working
days to collect the opinion from relevant departments. It takes another ten
working days to study the documents. (If the building is too high, approval from
aseismatic experts is needed. Then the approval time will be prolonged.)
|