Responsible Department: Shanghai Municipal
Development and Reform Commission (Department of Trade and
Development) Procedures: The applicant can entrust a qualified consultant
agency to compile project feasibility study report and submit all other relevant
documents. ---Feasibility Study Report to be submitted ----Project
Feasibility Study Report ----Valid Project Proposal Approval. Business
license and qualification of the applicant. Approval of location issued by urban
planning departments. Preliminary approval report of land administration
department on the use of land. Capital guarantee, approval of urban
infrastructure departments, overall floor plan and other
documents. Procedures: 1. The applicant shall submit the application to
Shanghai Municipal Development and Reform Commission. 2. For the basic
construction of commercial and modern logistic projects with more than RMB 30
million of investment, Shanghai Municipal Development and Reform Commission will
check with other relevant functional departments and give its decision
afterwards. Fees and Collection Standard: Submitted to: Address: Room
1108, #200 People's Avenue audituser According To: 1. "Circular on
Relaxing the Approval of Fixed Asset Investment and Simplifying Approval
Procedures" of the State Council (G.F. (1987) No.23) 2. Circular of the
Standing Committee of Shanghai Municipal National People's Congress No. 47,
September 2, 1996 Telephone: 63212810*2825£¬2826 Web-site: Working
Hours: Duration of Procedures: According to certain
regulations Qualification of Applicants: Investment enterprises (large-scale
enterprises registered within Shanghai: Headquarters, group companies,
share-holding companies) or enterprises with no supervising authorities but
registered at district (county) level development and planning
commissions |
|