The Approval and Submission of Project Proposal of Fixed Assets Investment Projects in the Field of Science and Technology, Information Industry and High and New Technology Industry (Domestic projects (domestic capital and foreign capital)
(06/21/2005)

Responsible Department: Shanghai Municipal Development and Reform Commission£¨Department of High-tech Industry£©
Procedures:
1. The construction project shall meet the requirement of Shanghai industrial development plan, and other relevant laws and regulations of the central and municipal government.
2. The applicant can entrust a qualified consultant agency to compile project feasibility study report and submit all other relevant documents.
----Project Proposal (Preliminary feasibility study report) to be submitted
----Project Proposal (Preliminary feasibility study report)
----Appendix
Procedures:
1. The application shall be submitted to Shanghai Municipal Development and Reform Commission after preliminary approval from supervising authorities and district (county) governments.
2. If the projects fall into the category in the charge of provincial and municipal government, Shanghai Municipal Development and Reform Commission will make the decision after consulting supervising authorities. If necessary, evaluation will be carried out. Final approval will be issued after project evaluation.
3. If the projects fall into the category in the charge of central government, the application will then be submitted to relevant departments of State Development and Reform Commission after preliminary checking of Shanghai Municipal Development and Reform Commission.
Fees and Collection Standard:
Submitted to:
Address: Room 1713B, #200 People's Avenue
audituser :
According To:
1. "Catalogue for the Guidance of Key Encouraged Foreign Investment Industries, Products and Technologies" of the State Planning Commission and State Economy and Trade Commission (revised on 2000)
2. "Circular on Opinions for the Implementation of High-tech Project Planning" of State Development and Planning Commission and Ministry of Finance (J.G.J. (2000) No.2433)
3. "Circular on Relaxing the Approval of Fixed Asset Investment and Simplifying Approval Procedures" of the State Council (G.F. (1987) No.23)
4. "Circular on Simplifying the Approval Procedure of Infrastructure Projects" of State Planning Commission (J.Z. (1984) No.684)
5. "Circular on Reaffirming the Importance of Act According to Infrastructure Construction and Approval Procedures" of the State Planning Commission (J.T.Z. (1999) No.693)
Telephone: 63212810*2861
Web-site:
Working Hours:
Duration of Procedures: According to certain regulations
Qualification of Applicants: Supervising authority or district (county) government