Responsible Department: Shanghai Municipal Development
and Reform Commission£¨Department of High-tech Industry£© Procedures: 1.
The construction project shall meet the requirement of Shanghai industrial
development plan, and other relevant laws and regulations of the central and
municipal government. 2. The applicant can entrust a qualified consultant
agency to compile project feasibility study report and submit all other relevant
documents. ----Project Proposal (Preliminary feasibility study report) to be
submitted ----Project Proposal (Preliminary feasibility study
report) ----Appendix Procedures: 1. The application shall be submitted
to Shanghai Municipal Development and Reform Commission after preliminary
approval from supervising authorities and district (county) governments. 2.
If the projects fall into the category in the charge of provincial and municipal
government, Shanghai Municipal Development and Reform Commission will make the
decision after consulting supervising authorities. If necessary, evaluation will
be carried out. Final approval will be issued after project evaluation. 3. If
the projects fall into the category in the charge of central government, the
application will then be submitted to relevant departments of State Development
and Reform Commission after preliminary checking of Shanghai Municipal
Development and Reform Commission. Fees and Collection Standard:
Submitted to: Address: Room 1713B, #200 People's Avenue audituser :
According To: 1. "Catalogue for the Guidance of Key Encouraged Foreign
Investment Industries, Products and Technologies" of the State Planning
Commission and State Economy and Trade Commission (revised on 2000) 2.
"Circular on Opinions for the Implementation of High-tech Project Planning" of
State Development and Planning Commission and Ministry of Finance (J.G.J. (2000)
No.2433) 3. "Circular on Relaxing the Approval of Fixed Asset Investment and
Simplifying Approval Procedures" of the State Council (G.F. (1987) No.23) 4.
"Circular on Simplifying the Approval Procedure of Infrastructure Projects" of
State Planning Commission (J.Z. (1984) No.684) 5. "Circular on Reaffirming
the Importance of Act According to Infrastructure Construction and Approval
Procedures" of the State Planning Commission (J.T.Z. (1999)
No.693) Telephone: 63212810*2861 Web-site: Working Hours: Duration
of Procedures: According to certain regulations Qualification of Applicants:
Supervising authority or district (county) government |