The Approval of Feasibility Study Report of Basic Construction Projects of Accommodation Facilities (hotels) for Tourism and Construction of Scenic Spots
(06/21/2005)

Responsible Department: Shanghai Municipal Development and Reform Commission£¨Department of Social Development£©
Procedures:
1. On the basis of Project Proposal, the applicant shall include market analysis, technology analysis, project design and investment-return analysis.
2. Land usage permit, planning permit and supporting facilities.
The applicant shall study the feasibility of its financing and entrust qualified consultant agencies to compile feasibility study report.
3. The applicant can entrust a qualified consultant agency to compile project feasibility study report and submit all other relevant documents.
---- Feasibility study report to be submitted
----Feasibility study report of the project
---- Appendix
Procedures:
1. The application shall be submitted to Shanghai Municipal Reform Commission, Shanghai Municipal Tourism Commission and Shanghai Municipal Foreign Investment Commission for approval before preliminary approval of supervising authorities or district (county) level governments. Shanghai Municipal Development and Reform Commission will be responsible for domestic-funded projects. Shanghai Municipal Foreign Investment Commission shall be responsible for the approval of foreign-invested projects.
2. If the projects fall into the category in the charge of provincial and municipal government, Shanghai Municipal Development and Reform Commission will make the decision after consulting supervising authorities. If necessary, evaluation will be carried out. Final approval will be issued after project evaluation.
3. If the projects fall into the category in the charge of central government, the application will then be submitted to relevant departments of State Development and Reform Commission after preliminary checking of Shanghai Municipal Development and Reform Commission.

Fees and Collection Standard:
Submitted to:
Address: Room 1101A, #200 People's Avenue
audituser :
1. According To: "Catalogue for the Guidance of Key Encouraged Foreign Investment Industries, Products and Technologies" of the State Planning Commission and State Economy and Trade Commission (revised on 2000)
2. "Circular on Opinions for the Implementation of High-tech Project Planning" of State Development and Planning Commission and Ministry of Finance (J.G.J. (2000) No.2433)
3. "Circular on Relaxing the Approval of Fixed Asset Investment and Simplifying Approval Procedures" of the State Council (G.F. (1987) No.23)
4. "Circular on Simplifying the Approval Procedure of Infrastructure Projects" of State Planning Commission (J.Z. (1984) No.684)
5. "Circular on Reaffirming the Importance of Act According to Infrastructure Construction and Approval Procedures" of the State Planning Commission (J.T.Z. (1999) No.693)
6. "Several Opinions on the Macro Control of Hotel Construction" of State Planning Commission and State Tourism Bureau (1999)
Telephone: 63212810*2964
Web-site:
Working Hours:
Duration of Procedures: According to certain regulations
Qualification of Applicants: Supervising authorities or district (county) level government