Home >> Service for Business >> Project Review >> Service Guide
The Approval of Project Proposal of Basic Construction Projects of Accommodation Facilities (hotels) for Tourism and Construction of Scenic Spots
(06/21/2005)

Responsible Department: Shanghai Municipal Development and Reform Commission£¨Department of Social Development£©
Procedures:
1. The construction projects shall meet the requirement of tourism development planning, urban planning and other laws and regulations of the central government.
2. The project shall meet the requirements of institution (facility) set-up. Have land usage right and other supporting facilities.
3. The project shall have good social and economic returns. The construction company shall be able to raise fund. It can entrust qualified consultant agencies to compile project proposal and submit it together with all other documents.
----Project Proposal to be submitted¡£
----Project Proposal¡£
---- Appendix
Procedures:
1. The application shall be submitted to Shanghai Municipal Reform Commission, Shanghai Municipal Tourism Commission and Shanghai Municipal Foreign Investment Commission for approval before preliminary approval of supervising authorities or district (county) level governments. Shanghai Municipal Development and Reform Commission will be responsible for domestic-funded projects. Shanghai Municipal Foreign Investment Commission shall be responsible for the approval of foreign-invested projects.
2. If the projects fall into the category in the charge of provincial and municipal government, Shanghai Municipal Development and Reform Commission will make the decision after consulting supervising authorities. If necessary, evaluation will be carried out. Final approval will be issued after project evaluation.
3. If the projects fall into the category in the charge of central government, the application will then be submitted to relevant departments of State Development and Reform Commission after preliminary checking of Shanghai Municipal Development and Reform Commission.

Fees and Collection Standard:
Submitted to:
Address: People's Avenue No.200 Room 1101A
audituser :
1. According To: "Catalogue for the Guidance of Key Encouraged Foreign Investment Industries, Products and Technologies" of the State Planning Commission and State Economy and Trade Commission (revised on 2000)
2. "Circular on Opinions for the Implementation of High-tech Project Planning" of State Development and Planning Commission and Ministry of Finance (J.G.J. (2000) No.2433)
3. "Circular on Relaxing the Approval of Fixed Asset Investment and Simplifying Approval Procedures" of the State Council (G.F. (1987) No.23)
4. "Circular on Simplifying the Approval Procedure of Infrastructure Projects" of State Planning Commission (J.Z. (1984) No.684)
5. "Circular on Reaffirming the Importance of Act According to Infrastructure Construction and Approval Procedures" of the State Planning Commission (J.T.Z. (1999) No.693)
6. "Several Opinions on the Macro Control of Hotel Construction" of State Planning Commission and State Tourism Bureau (1999)
Telephone: 63212810*2964
Web-site:
Working Hours:
Duration of Procedures: According to certain regulations
Qualification of Applicants: Supervising authority or district (county) level government