The Approval of Feasibility Study Report of Projects Financed Through or Not Through Urban Budget for Government Departments, Administrative and Legal System, Arm Forces, District and County Level Governments and Other Industries
(06/21/2005)
Responsible Department: Shanghai Municipal Development and Reform Commission (Department of Fixed Asset Investment)
Procedures:
1. Approval from urban planning, land administration, urban infrastructure departments and financing departments is needed before submitting the feasibility study report.
2. The construction company can entrust qualified consultant agency to compile feasibility study report and submit it together with all other relevant documents.
----Feasibility study report to be submitted
---- Feasibility Study Report of the Project
---- Appendix
Procedures:
1. Application of project proposal for large and medium-sized infrastructure projects in the charge of municipal governments compiled by qualified consultant agencies shall be submitted to Shanghai Municipal Development and Reform Commission with preliminary approval from supervising commission, district (county) level government and bureaus.
2. Shanghai Municipal Development and Reform Commission will work together with relevant government departments to check and evaluate the budgetary estimate according to the conditions and actual situation of the project. Approval of feasibility study report will be issued afterwards.
Fees and Collection Standard:
Submitted to:
Address: Room 1104A, #200 People's Avenue
audituser :
According To:
1. "Circular on Relaxing the Approval of Fixed Asset Investment and Simplifying Approval Procedures" of the State Council (G.F. (1987) No.23)
2. "Circular on Replace the Title 'Project Design' with 'Feasibility Study Report to be Submitted'" of State Planning Commission", (J.T.Z.(1991) No.1969)
3. "Circular of State Planning Commission on Budgetary Estimate of Large to Medium-size Projects Under Construction" distributed by Shanghai Municipal Planning Commission", (H.J.T.(96) No.425)
4. "Circular on Reaffirming the Importance of Act According to Infrastructure Construction and Approval Procedures" published by State Planning Commission (J.T.Z.(1999) No.693)
Telephone: 63212810-2806
Web-site:
Working Hours:
Duration of Procedures: According to certain regulations
Qualification of Applicants: Government departments, administrative and legal system, arm forces, district (county) level government and other industries with no supervising authorities