| The Approval of Feasibility Study Report of Projects Financed Through or Not Through Urban Budget for Government Departments, Administrative and Legal System, Arm Forces, District and County Level Governments and Other Industries
|
|
| (06/21/2005) |
Responsible Department: Shanghai Municipal Development and Reform
Commission (Department of Fixed Asset Investment) Procedures: 1. Approval
from urban planning, land administration, urban infrastructure departments and
financing departments is needed before submitting the feasibility study report.
2. The construction company can entrust qualified consultant agency to
compile feasibility study report and submit it together with all other relevant
documents. ----Feasibility study report to be submitted ---- Feasibility
Study Report of the Project ---- Appendix Procedures: 1. Application
of project proposal for large and medium-sized infrastructure projects in the
charge of municipal governments compiled by qualified consultant agencies shall
be submitted to Shanghai Municipal Development and Reform Commission with
preliminary approval from supervising commission, district (county) level
government and bureaus. 2. Shanghai Municipal Development and Reform
Commission will work together with relevant government departments to check and
evaluate the budgetary estimate according to the conditions and actual situation
of the project. Approval of feasibility study report will be issued
afterwards. Fees and Collection Standard: Submitted to: Address: Room
1104A, #200 People's Avenue audituser : According To: 1. "Circular
on Relaxing the Approval of Fixed Asset Investment and Simplifying Approval
Procedures" of the State Council (G.F. (1987) No.23) 2. "Circular on Replace
the Title 'Project Design' with 'Feasibility Study Report to be Submitted'" of
State Planning Commission", (J.T.Z.(1991) No.1969) 3. "Circular of State
Planning Commission on Budgetary Estimate of Large to Medium-size Projects Under
Construction" distributed by Shanghai Municipal Planning Commission",
(H.J.T.(96) No.425) 4. "Circular on Reaffirming the Importance of Act
According to Infrastructure Construction and Approval Procedures" published by
State Planning Commission (J.T.Z.(1999) No.693) Telephone:
63212810-2806 Web-site: Working Hours: Duration of Procedures:
According to certain regulations Qualification of Applicants: Government
departments, administrative and legal system, arm forces, district (county)
level government and other industries with no supervising authorities |
|
|