Responsible Department: Shanghai Municipal
Development and Reform Commission£¨Department of Urban Development
(Transportation Development)£© Procedures: The Project Launching Report
shall include the following: 1. Effective approval of preliminary
design 2. Approval of legal persons of the project 3. Certificate of
project capital 4. Valid bidding documents from project design, construction
and supervising companies 5. The construction materials and equipments
purchased can meet the requirements of construction for a certain period of
time 6. Other relevant requirements Procedures: 1. The applicant shall
submit the application to relevant commissions, departments, bureaus or district
(county) planning administrative departments, indicating the budgetary
estimate. 2. Relevant commissions, departments, bureaus or district (county)
planning administrative departments will state preliminary opinion and submit
the application to Shanghai Municipal Development and Reform Commission. 3.
Shanghai Municipal Development and Reform Commission will state its opinion
after taking into consideration the overall situation. The application will then
be submitted to State Development and Reform Commission. Fees and Collection
Standard: Submitted to: Address: Room 1102, #200 People's Avenue
audituser : According To: 1. "Circular on Relaxing the Approval of
Fixed Asset Investment and Simplifying Approval Procedures" of the State Council
(G.F. (1987) No.23) 2. "Several Regulations on Strengthening the
Administration of Infrastructure Projects" published by State Planning
Commission, State Construction Commission and the Ministry of Finance (J.J.
(1978) No.234) Telephone: 63212810*2859 Web-site: Working Hours:
Duration of Procedures: According to certain regulations Qualification of
Applicants: Urban infrastructure departments, water affairs department,
transportation bureaus, urban planning bureau, real estate company, urban
gardening bureau, environment and public hygiene departments, urban
afforestation departments |
|