The Checking and Approval of Adjusted Budgetary Estimate of Power Generator Construction Projects (Including pyroelectricity projects and resource utilization projects), Power Transformation Projects, Power Grid Construction Projects and Power Transformation Station Projects
(06/21/2005)

Responsible Department: Shanghai Municipal Development and Reform Commission£¨Department of Urban Development (Transportation Development)£©
Procedures:
The adjusted budgetary estimate shall include the following:
1. Valid approval of feasibility study report and preliminary design of the project
2. Budgetary estimate of the project and explanation on its adjustment provided by qualified engineering consulting companies.
3. Explanations provided by other departments on the change of construction condition.
4. Other relevant information to be provided.
Procedures:
Power generator construction projects (including pyroelectricity projects or projects that make comprehensive use of resources):
1. The applicant shall submit the application to Shanghai Municipal Development and Reform Commission.
2. Application of pyroelectricity projects whose single generator is below 25 mega-watts shall be approved by Shanghai Municipal Development and Reform Commission. Final approval will be issued after consulting other supervising departments.
3. Application of pyroelectricity projects whose single generator is above 25 mega-watts shall be submitted to State Development and Reform Commission with preliminary approval from Shanghai Municipal Development and Reform Commission.
Grid Construction Projects
1. Application for power transmission projects with transmission voltage under 110,000 voltage or certain regional power transmission or transformation projects at 220,000 voltage shall be submitted to Shanghai Municipal Development and Reform Commission by Shanghai Municipal Power Company.
2. Power transmission and transformation projects or supporting grid for power plants at 220,000 voltage or 500,000 voltage shall be submitted by Shanghai Municipal Power Company to Shanghai Development and Reform Commission for Preliminary approval before being submitted to State Development and Reform Commission.

Fees and Collection Standard:
Submitted to:
Address: Room 1102, #200 People's Avenue
audituser :
According To: 1. "Notice of the General Office of Shanghai Municipal Government on Issues Relating To the Transfer of Administrative Power or Power Supply Departments" (H.F.B.F.(2000) No.120)
Telephone: 63212810*2859
Web-site:
Working Hours:
Duration of Procedures: According to certain regulations