Responsible Department: Shanghai Municipal Development
and Reform Commission£¨Department of Urban Development (Transportation
Development)£© Procedures: The preliminary design shall include the
following: 1.Valid approval of the feasibility study report 2. Approval
from urban planning departments 3. Approval of land usage 4.Preliminary
design and budgetary estimate provided by qualified designing
companies 5.Opinions in written on project design from provided by urban
planning, environment protection, fire-proof, transportation, public health,
vaccination and workplace security departments Procedures: Power
generator construction projects (including pyroelectricity projects or projects
that make comprehensive use of resources): 1. The applicant shall submit the
application to Shanghai Municipal Development and Reform Commission. 2.
Application of pyroelectricity projects whose single generator is below 25
mega-watts shall be approved by Shanghai Municipal Development and Reform
Commission. Final approval will be issued after consulting other supervising
departments. 3. Application of pyroelectricity projects whose single
generator is above 25 mega-watts shall be submitted to State Development and
Reform Commission with preliminary approval from Shanghai Municipal Development
and Reform Commission.
Grid Construction Projects 1. Application for power
transmission projects with transmission voltage under 110,000 voltage or certain
regional power transmission or transformation projects at 220,000 voltage shall
be submitted to Shanghai Municipal Development and Reform Commission by Shanghai
Municipal Power Company. 2. Power transmission and transformation projects or
supporting grid for power plants at 220,000 voltage or 500,000 voltage shall be
submitted by Shanghai Municipal Power Company to Shanghai Development and Reform
Commission for Preliminary approval before being submitted to State Development
and Reform Commission. Fees and Collection Standard: Submitted to:
Address: Room 1102, #200 People's Avenue audituser : According To:
1. "Notice of the General Office of Shanghai Municipal Government on Issues
Relating To the Transfer of Administrative Power or Power Supply Departments"
(H.F.B.F.(2000) No.120) Telephone: 63212810*2859 Web-site: Working
Hours: Duration of Procedure: According to certain
regulations Qualification of Applicants: Investor of power
projects |