Responsible Department: Shanghai Municipal Development
and Reform Commission£¨Department of Urban Development (Transportation
Development)£© Procedure: The construction company can entrust qualified
consultant agency to compile feasibility study report and submit it together
with all other relevant documents. ----Project Proposal to be
submitted¡£ ---- Project Proposal (Initial Feasibility Study Report) ----
Appendix Procedures: Power generator construction projects (including
pyroelectricity projects or projects that make comprehensive use of
resources): 1. The applicant shall submit the application to Shanghai
Municipal Development and Reform Commission. 2. Application of
pyroelectricity projects whose single generator is below 25 mega-watts shall be
approved by Shanghai Municipal Development and Reform Commission. Final approval
will be issued after consulting other supervising departments. 3. Application
of pyroelectricity projects whose single generator is above 25 mega-watts shall
be submitted to State Development and Reform Commission with preliminary
approval from Shanghai Municipal Development and Reform Commission.
Grid Construction Projects: 1. Application for power
transmission projects with transmission voltage under 110,000 voltage or certain
regional power transmission or transformation projects at 220,000 voltage shall
be submitted to Shanghai Municipal Development and Reform Commission by Shanghai
Municipal Power Company. 2. Power transmission and transformation projects or
supporting grid for power plants at 220,000 voltage or 500,000 voltage shall be
submitted by Shanghai Municipal Power Company to Shanghai Development and Reform
Commission for Preliminary approval before being submitted to State Development
and Reform Commission. Fees and Collection Standard: Submitted to:
Address: Room 1102, #200 People's Avenue audituser : According To:
1. "Notice of the General Office of Shanghai Municipal Government on Issues
Relating To the Transfer of Administrative Power or Power Supply Departments"
(H.F.B.F.(2000) No.120) Telephone: 63212810*2859 Web-site: Working
Hours: Duration of Procedure: According to certain
regulations Qualification of Applicants: Investor of power projects
|