Responsible Department: Shanghai Municipal Development and Reform
Commission£¨Industry Development (Service Industry Development)£© Procedures:
The construction company can entrust qualified consultant agency to compile
feasibility study report and submit it together with all other relevant
documents. ----Preliminary budgetary estimate to be
submitted ----Preliminary budgetary estimate ---- Appendix Procedures:
1. State Development and Reform will entrust Shanghai Municipal Development
and Reform Commission to examine and approve the budgetary estimate of
preliminary design. The application will be submitted to Shanghai Municipal
Development and Reform Commission with preliminary approval from supervising
authority and district (county) level governments. 2. Shanghai Municipal
Development and Reform Commission will check and pprove together other
functional departments. Fees and Collection Standard: Submitted to:
Address: Room 1713C, #200 People's Avenue audituser : According To:
1. "Circular on Relaxing the Approval of Fixed Asset Investment and
Simplifying Approval Procedures" of the State Council (G.F. (1987) No.23) 2.
Notice of the Standing Committee of Shanghai Municipal People's Congress, No.47
published on September 2, 1996 3. According to certain regulations of the
central or municipal government on capital use (finance, national debt and
guiding capital) 4. Relevant documents of State Development and Reform
Commission on entrusting Shanghai Municipal Planning Bureau to examine and check
the budgetary estimate of preliminary design (implementation
scheme) Telephone: 63212810¡ª2842 Web-site: Working Hours: Duration
of Procedures: According to certain regulations Qualification of Applicants:
Supervising authority of the applicant or district (county) level government
|
|