(1) For authorized operators, an "Examination Form for a Public Mobile
Communication Base Station Location" must be filled out and submitted when
setting up or adding base stations for mobile communication.
(2) The Shanghai Radio Management Office will reply to the submitted
"Examination for a Public Mobile Communication Base Station Location" within 15
days. The "Authorization for a Public Mobile Communication Base Station
Location" will be awarded if the application is approved.
(3) The operators shall apply for a "Certificate of Environmental
Electromagnetic Radiation" immediately after the station is built. The
environmental protection administration shall perform tests within three months
of the trial operation, and award the "Certificate of Environmental
Electromagnetic Radiation" after approval.
(4) The operators can apply for radio station licenses with the
"Authorization for a Public Mobile Communication Base Station Location", the
"Technical Specification of the Radio Station" and the "Certificate of
Environmental Electromagnetic Radiation".
|